Construction Period of Riyadh Metro Package 3 Changed
2022. 06. 21
<p>Samsung C&T and the consortium partners have negotiated with the contract owner, The Royal Commission for Riyadh City, to extend the project completion date of Riyadh Metro Package 3.</p><p> </p><p>- Construction period: before change) October 1, 2013 ~ TBD</p><p> after change) October 1, 2013 ~ 2024-04-30</p><p><br></p><p><br></p><p>- Contract owner: before change) High Commission for the development of Arriyadh, Arriyadh Development Authority</p><p> after change) The Royal Commission for Riyadh City</p><p><br></p><p>※ Overview of project</p><p>- Title of contract: Riyadh Metro Package3<br></p><p>- Contract amount: USD 2,426,809,931 (forSamsung C&T)</p><p>- Contract owner: The Royal Commissionfor Riyadh City</p><p>- Construction period: October 1, 2013 ~ 2024-04-30</p>